Cirebon 1 (660MW)
Status: Financial Close /Â Operational
On 8 March 2010, financial close was achieved for the US$850 million, 660MW Cirebon 1 Independent Power Project (IPP) coal-fired power station in Cirebon, West Java, Indonesia.
-
Debt/Equity 70:30
-
Debt guaranteed by JBIC and Kexim
-
Contract: Build-Own-Operate (BOO)
-
PPA: 30 years
Parties to deal
Awarding authority
PT PLN (Persero)
Sponsors
| Sponsor | Ownership (%) | Equity (US$m) |
|---|---|---|
| Marubeni Corporation | 32.5 | 83 |
| Korea Midland Power | 27.5 | 70 |
| PT Tripatra Engineers & Constructors | 20 | 51 |
| Samtan | 20 | 51 |
| Total | 100 | 255 |
Lenders
| Lender | % of total debt | Debt (US$m) |
|---|---|---|
| Japan Bank for International Cooperation (JBIC) | 36 | 214 |
| Export-Import Bank of Korea | 24 | 143 |
| Bank of Tokyo-Mitsubishi UFJ | 10 | 60 |
| ING Group | 10 | 60 |
| Mizuho Financial Group | 10 | 60 |
| Sumitomo Mitsui Banking Corporation | 10 | 60 |
| Total | 100 | 595 |
Advisers
| Adviser | Role |
|---|---|
| ING Group | Financial Adviser to the sponsors |
| Paul Hastings | Legal Adviser to the sponsors |
| Makarim & Taira S | Legal Adviser to the sponsors – local counsel |
| Milbank, Tweed, Hadley & McCloy | Legal Adviser to the lenders |
| Ali Budiardjo, Nugroho, Reksodiputro (ABNR) | Legal Adviser to the lenders – local counsel |
| Yulchon | Legal Adviser to the lenders – Korean counsel |
| Wong Partnership | Legal Adviser to the lenders – Singapore counsel |
| Latham & Watkins | Legal Adviser to KOMIPO |
| Baker & McKenzie | Legal Adviser to PT PLN Persero |
Debt structure
Debt structure
| Facility type | Debt (US$m) | Lenders | Maturity (date) |
|---|---|---|---|
| Term loan | 214 | JBIC | 21 April 2028 |
| Term loan | 143 | Kexim | 21 April 2028 |
| Term loan | 143 | BTMU ING Mizuho SMBC |
21 April 2028 |
| Term loan | 95 | BTMU ING Mizuho SMBC |
21 April 2028 |